20 Oct 2026
Please be informed that the male toilet at HKU B-Active will undergo refurbishment from 2 November to 31 December 2026 (both dates inclusive). The work will be carried out in two phases:
A) Phase 1: Urinal Work
- 2 November – 9 December 2026: Urinals will be closed; toilet cubicles will remain open.
- 5 and 6 November 2026: Noisy work is scheduled for these two days. During this period, the entire male toilet will be temporarily closed.
B) Phase 2: Basin and Pipe Work
- 10 – 31 December 2026: The entire male toilet will be closed.
- Please note that some noise and dust may occur intermittently during this phase. We will take reasonable measures to minimize disruption and keep the area as clean as possible.
We apologize for any inconvenience caused and appreciate your understanding and cooperation during this period.